By Akinwande Soji-Ojo
The current epileptic power supply being experienced across the country may get worse in the coming days as the National Control Centre (NCC) of the Transmission Company of Nigeria (TCN) has ordered the shutting down of the 504mw Alaoji and 336mw Olorunsogo power stations.
According to The Nation, the NCC predicated the decision on the refusal of the Electricity Distribution Companies (DisCos) to accept their load allocations.
“NCC has asked Alaoji and Olorusogo power plants to shut down.
“It (NCC) said it would not take power from them,” the medium quoted the source as saying.
Aside from the hydropower plants, the NDPHC (thermal plants) are the cheapest power generators in Nigeria.
The medium, however, reported that the NCC would prevail on the NIPPs to shutdown instead of the private power generating firms that vend electricity at the highest prices.
It was gathered that the easy recourse to the NDPHC to shutdown is based on sharp practices as it has neither any commercial nor technical reason.
Decrying the corrupt practices and sabotage that have permeated the electricity market, the source said: “These are the unimaginable issues we are facing in this business.
“You know that the NDPHC is the cheapest of all the power plants.
“Our power is the cheapest aside hydro. And of all the thermal plants (NDPHC) is the cheapest because it is said that it is owned by the nation.
“But even as it is the cheapest, is it not supposed to be made attractive so that it will be beneficial to the public?
“But do you know what they do? They will first of all buy from all the other ones and it is only when others cannot supply that they will buy from us.
“And if they say it is getting too much, it is us they will first ask to shut down,” she said.
It was also gathered that the Nigeria Bulk Electricity Trading Company (NBET) owes the NDPHC N170 billion for generated power.
“The NDPHC is owed N170billion but being a government entity, it cannot complain as the private ones,” the source said.
On load rejection, the source noted: “If they (DisCos) say they don’t want power, it is NDPHC they will first ask to go off the grid.
“Any time they have more power than they need the grid will be affected. They will ask some generation companies to shutdown and the first one is NDPHC.
“It is scandalous if you know how many megawatt we are producing now for the whole country.”
The Nigerian Electricity System Operator (SO) of the TCN report of April 27 indicated that there was 3238.40mw energy generation.
It also showed that total energy sent out was 4,046.3mw while the total generated was 4103.5mw.
Executive Director, Research and Advocacy of the Association of Nigeria Energy Distributors, Chief Sunday Oduntan, said the allegation of load rejection was not true.
Reacting to the news that the DisCos were rejecting their load allocations, he simply said “No.”